TEXAS A&M UNIVERSITY KRUEGER HALL
COLLEGE STATION, TEXAS
Brandt performed a redesign of the HVAC system of Texas A&M University’s Krueger Hall to upgrade the original system, built in 1972. The work in the residence hall consisted of removing the existing HVAC system and replacing it with new RTU equipment, pumps, specialties, and fans. Brandt also replaced the existing control system with an upgraded BMS system. As prime contractor, Brandt oversaw all electrical, structural, concrete, and fire protection trades. Eighty percent (80%) of the project was completed in 77 days during Summer Break.
PROJECT TEAM
Owner: Texas A&M University System SSC
Engineer: Ramirez-Simeon Engineering
Architect: SZH Architecture
Contractor: The Brandt Companies, LLC
PROJECT DETAILS
Project Size: 120,000sf
Start/Completion Date: 12/2015 – 07/2016
Brandt Roll: Mechanical Services